Industrial electric furnace power distribution and heating time requirements

Industrial electric furnace power distribution and heating time requirements

Industrial electric furnace power distribution and heating time requirements:

A Resistance furnace installed power distribution

① Box furnace: door installed with 1/3-1/4 power;
② Pit type furnace: L/D = zone number (L: height, D: diameter)
③ Continuous furnace: power distribution determined by technology curve, but also increase the power at the furnace mouth;
④ Furnace temperature and power distribution:

a. 1200 ℃: 15-20Kw/m2;
b. 1000 ℃: 10–15 Kw/m2;
c. 700 ℃: 6–10 Kw/m2;
d. 400 ℃: 4–7 Kw/m2.

B Industrial furnace heating time requirements:

① Use the refractory furnace lining:

a. Small furnace: 1.5-2 hours;
b. Medium furnace: 2-3 hours.

② By using of fiber furnace lining:

a. Small furnace: 1-2 hours;
b. Medium furnace: 1.5-2 hours;
c. Continuous furnace: heating rate (Max.) 50 ℃/hour.

Industrial electric furnace power distribution and heating time requirements

Industrial electric furnace power distribution and heating time requirements

Industrial electric furnace combine with temperature control system for using. Furnace temperatures can be controlled automatically or manually, also users can request a computer table or equipped with computers to do multi-temperature control to ensure products quality. If electric furnace as cycle mode of operation. Rated temperature of 600 ℃ -1800 ℃, which used for metal parts for normalizing, annealing, quenching and other heating purposes in oxidizing atmosphere.